Project Intelligence
Track 13 real estate projects across NCR. Legal status, risk analysis, and market intelligence updated from court records and news sources.
Filters
13 of 13 projects
low
New LaunchACE Verde
ACE Group
Sector 22A, Greater Noida
7 towers · 1,287 units
Updated 30 Sept
high
Partial PossessionAmrapali Dream Valley
Amrapali · Amrapali Group
Tech Zone IV (GH-09), Greater Noida
47 towers · 16,000 units
RERA Non-Compliant10+ Years Delayed+1 more
Updated 30 Sept
critical
AbandonedChintels Paradiso
Chintels
Sector 109, Gurgaon
9 towers · 542 units
Flat Registries BlockedSupreme Court Stay Active+1 more
Updated 30 Sept
low
New LaunchCocoa County
County Group
Sector 88A, Gurgaon
TBC · TBC
Updated 30 Sept
critical
Partial PossessionIreo Victory Valley
Ireo
Sector 67, Gurgaon
30 towers · 868 units
ED Investigation Active5+ Years Delayed
Updated 30 Sept
high
Partial PossessionJaypee Wish Town
Jaypee · Jaiprakash Associates
Sectors 128–134, Noida
84 towers · 32,000 units
ED Investigation ActiveAuthority Dues Unpaid+1 more
Updated 30 Sept
low
Under ConstructionM3M The Cullinan
M3M · M3M India Group
Sector 94, Noida
5 towers · TBC
Updated 30 Sept
critical
Under CIRPSupertech Eco Village 2
Supertech · Supertech Group
Sector 10, Greater Noida West, Greater Noida
TBC · TBC
Under Insolvency ProcessED Investigation Active+3 more
Updated 30 Sept
high
Partial PossessionUnitech Vistas
Unitech
Sector 70, Gurgaon
23 towers · 1,196 units
10+ Years Delayed
Updated 30 Sept
critical
Partial PossessionLotus 300
Lotus · 3C Group
Sector 107, Noida
6 towers · 330 units
Under Insolvency ProcessSupreme Court Stay Active+5 more
Updated 29 SeptNext hearing: 30 Sept
critical
Under CIRPLotus Isle
Lotus Greens · 3C Group
Sector 98, Noida
3 towers · 258 units
Under Insolvency ProcessAuthority Dues Unpaid+3 more
Updated 29 Sept
high
Under CIRPLotus Panache
Lotus · 3C Group
Sector 110, Noida
31 towers · 4,018 units
Under Insolvency ProcessAuthority Dues Unpaid+1 more
Updated 29 Sept
high
Under CIRPLotus Zing
Lotus · 3C Group
Sector 168, Noida
15 towers · 2,464 units
Under Insolvency ProcessAuthority Dues Unpaid+2 more
Updated 29 Sept